Construction of a Tunnel Under the Dnieper in Kyiv: Experts Assess Realistic Timelines

🚌 Transport 2 min read 👁 3

Implementing a major infrastructure project in the capital could take up to seven years. Experts highlight the complexity of preparatory work and bureaucratic procedures.

Construction of a Tunnel Under the Dnieper in Kyiv: Experts Assess Realistic Timelines🚌Transport

Photo: UNIAN

Key points

  • Optimistic construction timeline is 5-7 years
  • Tender procedures may take about a year
  • Floating bridges and river transport are being considered as alternatives

Prospects for Underground Connectivity

The issue of building a tunnel under the Dnieper in Kyiv has once again become a subject of debate among specialists. Despite interest from international partners, particularly the American company Robbins, experts warn against excessive optimism regarding the speed of implementation. Oleksandr Davydenko, an associate professor at the Department of Bridges and Tunnels at the National Transport University, emphasizes that the tender process alone could take up to a year.

Timelines and Alternatives

According to the expert's estimates, the optimistic scenario for completing the structure is between 5 and 7 years. This differs significantly from government projections, which previously suggested the possibility of finishing the work in 2-3 years. The main challenges lie in the complexity of logistics, the provision of specialized equipment, and the development of project documentation.

  • The estimated cost of the simplest tunnel option is $500 million.
  • Floating bridges, which can be constructed in a matter of weeks, are being considered as a temporary solution.
  • River transport remains an alternative, but its effectiveness is limited by security risks during air raid alerts.

The project preparation phase is currently underway. Attracting foreign technologies should assist Ukrainian specialists in executing this complex engineering task, though the priority remains finding the most rational ways to connect the capital's banks.

Source UNIAN — unian.ua/economics/transport/tunel-pid-dniprom-u-kiyevi-ne-pobuduyu… ↗